The 550kV GIS bushing is applied to the 500kV Wenting substation

On March 26, 2015, the No. 1 and No. 4 main substation of 500kV Wenting substation was successfully delivered, marking the completion and operation of the 500kV Wenting power transmission and transformation project.


   

In this substation, the 550kV GIS incoming and outgoing line bushing used is manufactured by PEIPORT. It plays an insulating role by connecting GIS equipment busbar and introducing current carrying conductors. Our company's high quality product design, to ensure that the product has excellent electrical insulation performance.

 


The 500kV Wenting transmission line project starts from the Heze Power Plant of Huarun and runs through Mudan District, Dingtao County and Chengwu County of Heze City, with a length of 54.198 kilometers. The whole line with the tower double circuit erection.This is the first 500 kV project completed and put into operation by the State Grid Shandong Electric Power Company this year, which will effectively relieve the power supply pressure of Heze Southern Power Grid and improve the reliability of power supply.

HOME   |   ABOUT   |   NEWS   |   PRODUCT   |   PROJECT   |   CONTACT
Copyright: Shandong Peiport Electric Power Science &Technology Co., Ltd Lu ICP Bei 05024719